Greenfield Fire Department, MA – Job 43749
Greenfield Fire Department, MA – Job# 43749 April 26, 2025: The cab completed fabrication and was staged. In the next report the cab may begin
Greenfield Fire Department, MA – Job# 43749 April 26, 2025: The cab completed fabrication and was staged. In the next report the cab may begin
Holderness Fire Department, NH – Job# 40837 April 26, 2025: The cab began the paint process and the pump house finished final pump assembly. The
Lowell Fire Department, MA – Job# 40775 April 26, 2025: The cab began the paint process with metal finishing. In the next report the cab
Lisbon Fire Department, ME – Job# 40204 April 26, 2025: The new Pierce apparatus is now in production at the Bradenton Floreida facility. This week
Lewiston Fire Department, ME – Job#39538 April 26, 2025: Your cab has completed fabrication. View Full Report May 2, 2025: The cab began the paint
Saugus Fire Department, MA – Job# 39445 April 26, 2025: The Pierce apparatus is now in production! View Full Report May 2, 2025: In this
Concord Fire Department, NH – Job# 39341 April 26, 2025: The cab was staged to continue through paint. In the next report, the cab may
Lowell fire department, ma – job# 40773 May 2, 2025: The cab began the paint process with metal finishing. View Full Report May 9, 2025:
Raymond Fire Department, ME – Job# 39469 May 2, 2025: The apparatus is now in production! View Full Report May 9, 2025: The cab completed

METHUEN FIRE DEPARTMENT, MA – JOB# 41254 METHUEN FD, MA PIERCE SABER FR PUMPER April 12, 2025: The cab was in staging and the pump