Category: In Production

MERRIMACK, NH -JOB #35860-02

Apr 22, 2021 by allegiancefr

Overview / Update Job #35860-02

Week ending May 8, 2021  –This week the cab continued the paint process and the chassis frame arrived. T he pump house structure along with the fire pump remained in staging (no photos ) and the body began the paint process . Next week the cab should finish with paint and the chassis frame should continue with assembly . The pump house structure should be joined with the fire pump and the body should finish with paint.

Latest from the Factory Floor

CAMBRIDGE, MA -JOB #35479

Apr 22, 2021 by allegiancefr

Overview / Update Job #35479

Week ending May 7, 2021  –This week the cab was in staging (no photos) and the fire pump continued to receive valves and plumbing. The body began the paint process . Next week the cab should begin the paint process and the chassis frame may arrive. The pump house structure should begin fabrication and the fire pump should continue to receive valves and plumbing. The body should finish with paint.

Latest from the Factory Floor

PROVIDENCE, RI -JOB #35599

Apr 15, 2021 by allegiancefr

Overview / Update Job #35599

Week ending May 7, 2021  –In this report your cab is continuing assembly, the frame assembly continued, the transverse compartment completed paint , and both body modules made progress in paint however the rear body was not available for photos. In your next report your cab and transverse compartment may be merged with the chassis while to body modules may make progress in paint.

Latest from the Factory Floor

BRATTLEBORO, VT -JOB #35857

Apr 15, 2021 by allegiancefr

Overview / Update Job #335857

Week ending May 8, 2021  –This week the cab was in staging (no photos) and the fire pump continued to receive valves and plumbing. The body began the paint process . Next week the cab should begin the paint process and the chassis frame may arrive. The pump house structure should begin fabrication and the fire pump should continue to receive valves and plumbing. The body should finish with pain t .

Latest from the Factory Floor

SHEFFIELD, MA -JOB #35583

Apr 8, 2021 by allegiancefr

Overview / Update Job #35583

Week ending May 7, 2021  –In this report your cab completed assembly while the frame build began, and the body completed paint. In your next report your cab may be staged, the frame build may continue, and the body may begin initial assembly.

Latest from the Factory Floor

MERRIMACK, NH -JOB #35860-01

Apr 8, 2021 by allegiancefr

Overview / Update Job #35860-01

Week ending May 8, 2021  –This week the cab began to receive trim and wiring harnesses , and the chassis frame continued with assembly. The fire pump made no progress (no photos), and the body finished the paint process. Next week the cab should continue to receive trim and wiring harnesses and the chassis frame should continue with assembly. The pump house structure should begin fabrication and the fire pump should continue to receive valves and plumbing. The body should continue to receive trim and wiring harnesses.

Latest from the Factory Floor

LAWRENCE, MA -JOB #35794

Apr 8, 2021 by allegiancefr

Overview / Update Job #35794

Week ending May 7, 2021  –In this report your cab started assembly while the pump house is staged, and the body is in queue to start paint . In your next report your cab may continue assembly while the pump house is staged, and the body may begin paint.

Latest from the Factory Floor