ATTLEBORO, MA -JOB #35043

Sep 30, 2020

Overview / Update Job #35043

Week ending October 16, 2020  –This week your cab began the content installation process, your chassis remained in queue to begin to have powertrain components installed, your pumphouse went through the paint process, and your body completed the paint process . Next week both your cab and pumphouse may be installed on your chassis.

Latest from the Factory Floor

Leave a Reply

Your email address will not be published. Required fields are marked *