Overview / Update Job #335857

Week ending May 29, 2021  –This week the cab continued to receive trim and wiring harnesses and the chassis frame continued with assembly . The fire pump was in staging and the body finished the paint process. Next week the cab should finish with trim and wiring harnesses and the chassis should continue with assembly. The pump house structure and fire pump should be joined, and the body should begin to receive trim and wiring harnesses.