In-Production

Winhall VT Job# 40305

Written by AFR Team | Jul 10, 2026 4:12:29 PM

In-Production Apparatus

Job# 40305

Status Update

July 11, 2026

In this report your apparatus completedfinal assemblyand released to test. In the next report testing may continue.

Status Update

June 26, 2026

In this report your apparatus continuedfinal assembly. In the next report final assembly may be complete followed by release to test.

Status Update

June 19, 2026

In this report your apparatus began final assembly. In the next report final assembly may continue.

Status Update

June 12, 2026

In this report your cab, pump house, and body were merged with the frame at the start of initial apparatus assembly. In the next report your apparatus may begin final assembly.

Status Update

June 05, 2026

In this report your cab completedinitial assembly, the frame build began, the pump house completed initial assembly, and the body completed paint and began initial assembly. In the next report your cab and pump house may be merged with the frame while the body may complete initial assembly.

Status Update

May 22, 2026

In this report your cab continued initial assembly, the pump house continued initial assembly, and the body completed fabrication but was unavailable for photos. In the next report bothyourcabandthe pumphousemay continue initial assembly while the body may be available to photograph.

Status Update

May 15, 2026

In this report your cab completed paint and began initial assembly, the pump house was painted then started initial assembly, and the body began fabrication. In the next report your cab may continue initial assembly, the pump house may continue initial assembly, and the body may complete the fabrication process.

Status Update

May 08, 2026

In this report your cab continued the paint process while the pump house structure was fabricated. In the next report your cab may continue through paint while the pump house structure may be staged.

Status Update

May 01, 2026

In this report your cab continued through paint. In the next report your cab may continue the paint process.

Status Update

April 24, 2026

In this report your cab completed fabrication and began the paint process with metal finishing. In the next report your cab may continue through paint.

Status Update

April 17, 2026

In this report your cab continued thefabricationprocess. In the next report your cab may complete fabrication.

Initial Report

April 10, 2026

Congratulations -Your new Pierce apparatus is now in production! This week your cab began fabrication. In the next report your cab may continue the fabrication process.