Lowell Fire Department, MA - 40771-01-05
Five New Pierce Enforcer Pumpers are in production at the Appleton, WI factory! This latest addition to the Lowell, MA fleet features a 1500 GPM Waterous CSU, 750 gallon New York Style water tank, powered by a 450 HP Cummins L9 Engine We are excited to be building these order for Lowell Fire Department. Be sure to check out the latest weekly updates below for behind-the-scenes photos straight from the factory floor.
Lowell FD's Pierce Enforcer Pumper
UPDATES FROM THE FACTORY FLOOR!
40771-01
October 4, 2024: In this report the cab continued initial assembly, the pump house structure was fabricated and the body began the paint process.
40771-02
October 4, 2024: In this report the cab began initial assembly, the pump house structure was fabricated and the body began fabrication.
40771-03
October 4, 2024: In this report the cab completed paint and was staged. The pump house structure was fabricated, and the body began fabrication.
40771-04
October 4, 2024: In this report the cab completed paint and was staged, the pump house structure was fabricated, and the body began fabrication.
40771-05
October 4, 2024: In this report, the cab completed paint and was staged. The pump house structure was fabricated and the body began fabrication.
40771-01
October 11, 2024: The cab completed initial assembly and was installed on the frame. The Pump house began initial assembly and the body completed paint and initial assembly.
40771-02
October 11, 2024: The cab continued initial assembly, the frame build began, the pump house began initial assembly, and the body began the paint process.
40771-03
October 11, 2024: The cab began initial assembly, the frame build began, the pump house began initial assembly, and the body completed fabrication.
40771-04
October 11, 2024: The cab began initial assembly, the frame build began, the pump house structure started initial assembly, and the body completed fabrication.
40771-05
October 11, 2024: The cab began initial assembly, the frame build began, the pump house structure remained staged, and the body completed fabrication.
40771-01
October 25, 2024: The apparatus completed initial assembly and began final assembly.
40771-02
October 25, 2024: The pump house was painted, completed initial assembly, and was installed on the chassis followed by the body being merged while initial apparatus assembly continued.
40771-03
October 25, 2024: Both the pump house and body completed initial assembly and were merged with the chassis while assembly continued.
40771-04
October 25, 2024: The chassis was staged to continue assembly, the pump house continued initial assembly, and the body completed paint and initial assembly.
40771-05
October 25, 2024: The chassis was staged to continue assembly. The pump house continued initial assembly and the body completed paint, and began initial assembly.
40771-01
November 1, 2024: The apparatus started final assembly and testing, then released to quality and graphics where any remaining content will be applied.
40771-02
November 1, 2024: The apparatus began completed initial assembly and began final assembly.
40771-03
November 1, 2024: The apparatus began completed initial assembly and began final assembly.
40771-04
November 1, 2024: The pump house completed initial assembly and was installed on the chassis along with the body.
40771-05
November 1, 2024: The chassis remained staged, the pump house was painted and the body completed initial assembly.
40771-01
November 7, 2024: The apparatus continued the quality and graphics process where any remaining content will be applied. Once finished it will be made ready for the customer acceptance inspection.
40771-02
November 7, 2024: The apparatus continued the quality and graphics process where any remaining content will be applied. Once finished it will be made ready for the customer acceptance inspection.
40771-03
November 1, 2024: The apparatus completed final assembly and test followed by release to quality and graphics where any remaining content will be applied. Once finished, it will be made ready for customer acceptance inspection.
40771-04
November 1, 2024: The apparatus completed final assembly and test followed by release to quality and graphics where any remaining content will be applied. Once finished, it will be made ready for customer acceptance inspection.
40771-05
November 1, 2024: The pump house and body were merged with the chassis followed by the completion of final assembly and test. The apparatus was released to quality and graphics where any remaining content will be applied. Once finished it will be made ready for customer acceptance inspection.