Merrimack Fire Department, NH- Job #38808
The Merrimack, NH Fire Department’s cutting-edge Pierce Enforcer 100′ Ascendant Aerial Tower is currently in production! Equipped with a robust Hale 1500GPM pump and powered by a Cummins X12 500hp motor, this aerial tower promises unparalleled performance and reliability. See more info about design and performance below and stay tuned for updates from the Pierce factory floor as we bring this impressive apparatus to life!
- Cab: 7000 Enforcer Cab
- Chassis: Enforcer chassis
- Body: 100′ Ascendant Aerial Tower Alum Body
- Bumper: 21″ Painted Aluminum
- Engine: 500 HP Cummins X12 Engine
- Transmission: Allison 5th Gen, 4000 EVS P
- Axle Front: 21,500 lb Dana Axle
- Axle Rear: 54,000 lb Meritor Axle
- Water Tank: 300 Gallon Poly Water Tank
- Pump House: 36″ Control Zone Side Mount
- Pump: 1500 GPM DSD Hale Single Stage
- Crosslays: (2) 1.50″, With Trays, 200′
updates from the factory floor!
March 23, 2024: Merrimack FD’s Aerial Tower is now in production! This week the cab completed fabrication and began the paint process! Next week the cab may continue through paint.
March 29, 2024: This week the cab continued through paint, while the front body module began fabrication! Next week both processes will continue.
April 6, 2024: This week the cab completed paint, the front body module completed fabrication, and the rear body module began fabrication. Next week the front body module may continue through paint!
April 14, 2024: This week the cab began initial assembly, the pump house structure was fabricated, the front body module completed paint, and the rear body module completed fabrication! Next week the cab may continue initial assembly, and the pump house structure may be painted.
April 20, 2024: This week the cab completed initial assembly, the pump house began initial assembly, and the rear body module was staged to begin the paint process! Next week the pump house may continue initial assembly, and the rear body module may continue through paint.
April 27, 2024: This week the pump house completed initial assembly, and the rear body module completed paint! Next week the rear body module may begin initial assembly.
May 4, 2024: This week the frame build began, and the front body module completed initial assembly! Next week the rear body module may began initial assembly.
May 11, 2024: This week the frame build continued, while the rear body module completed initial assembly. Next week the cab and pump house may be installed on the frame, and the torque box may begin initial assembly.
May 18, 2024: This week the body and pump house were installed on the frame, while the torque box began initial assembly. Next week the torque box may be merged with the chassis!
May 25, 2024: This week the torque box was merged with the chassis, and the rear body module was installed. The apparatus has begun final assembly! Next week the front body module may be installed, and final assembly will continue.
June 1, 2024: This week the front body module was merged while the apparatus continued final assembly! Next week the apparatus may complete final assembly and release to initial testing!
June 8, 2024: This week the apparatus completed final assembly and released to initial testing! Next week the apparatus may remain staged to continue testing.
June 15, 2024: This week the apparatus remained staged. Next week the apparatus may remain staged for aerial pin.
June 21, 2024: This week the apparatus remained staged while the aerial device arrived and began initial assembly! Next week the aerial device may continue initial assembly.
July 12, 2024: This week the apparatus completed testing followed by release to quality and graphics where any remaining content will be applied. Once finished, it will be made ready for customer acceptance inspection. This is the last scheduled report for this apparatus.
WEEKLY REPORTS:
- Merrimack-March 23, 2024
- Merrimack-March 29, 2024
- Merrimack-April 6, 2024
- Merrimack-April 14, 2024
- Merrimack-April 20, 2024
- Merrimack-April 27, 2024
- Merrimack-May 4, 2024
- Merrimack-May 11, 2024
- Merrimack-May 18, 2024
- Merrimack-May 25, 2024
- Merrimack-June 1, 2024
- Merrimack-June 8, 2024
- Merrimack-June 15, 2024
- Merrimack-June 21, 2024
- Merrimack-July 12, 2024