Status Update
May 08, 2026
In this report final assembly continued. In the next report your apparatus may complete final assembly followed by release to testing.
Status Update
May 01, 2026
In this report your cabandpumphousewere merged with the frame followed by body installation then the start of final assembly. In the next report final assembly may continue.
Status Update
April 24, 2026
In this report your cab was staged, the frame build continued, the pump house was staged, and the body completed initial assembly. In the next report your caband pump house may be merged with the frame followed by body installation at the start of initial apparatus assembly.
Status Update
April 17, 2026
In this report your cab completedinitial assembly,the frame build began, the pump house completed initial assembly, and the body completed paint and wasstaged. In the next report your cab may be staged, the frame build may continue, the pump house may bestaged, and the body may remain staged to begin initial assembly.
Status Update
April 10, 2026
In this report your cab began initial assembly, the pump house was painted then staged to continue initial assembly, and the body began the paint process. In the next report your cab may continue initial assembly, the pump house may continue initial assembly, and the body may continue through paint.
Status Update
April 04, 2026
In this report your cab completedfabricationand was staged, the pump house began initial assembly, and the body was fabricated. In the next report your cab may begin initial assembly, the pump house may continue initial assembly, and the body may begin the paint process.
Initial Report
March 20, 2026