Status Update

October 30, 2026Final Report

In this report your apparatus was staged to complete testingand alignment. When testing completes it will release to quality and graphics where any remaining content will be applied.Once finished it will be made ready for your customer acceptance inspection.

Photo 1Photo 2Photo 3Photo 4
Photo 5Photo 6Photo 7Photo 8
Photo 9Photo 10Photo 11Photo 12
Photo 13Photo 14Photo 15Photo 16
Photo 17Photo 18Photo 19Photo 20
Photo 21Photo 22Photo 23Photo 24
Photo 25Photo 26Photo 27Photo 28
Photo 29Photo 30Photo 31Photo 32
Photo 33Photo 34Photo 35Photo 36
Photo 37Photo 38Photo 39Photo 40
Photo 41Photo 42Photo 43Photo 44
Photo 45Photo 46Photo 47Photo 48
Photo 49Photo 50Photo 51

Status Update

October 23, 2026

In this report your apparatus continued testing. In the next report testing may be complete and your apparatus may release to quality and graphics where any remaining content will be applied.

Photo 1Photo 2Photo 3

Status Update

October 16, 2026

In this report your apparatus completedfinal assemblyand released to test. In the next report testingmay continue.

Photo 1Photo 2Photo 3Photo 4

Status Update

October 02, 2026

In this report your apparatus continued final assembly. In the next report final assembly may be complete followed by release to alignment and testing.

Photo 1Photo 2Photo 3Photo 4

Status Update

September 25, 2026

In this report the body was merged with the chassis followedbythestartoffinalassembly. In the next report your apparatus may continue final assembly.

Photo 1Photo 2Photo 3Photo 4

Status Update

September 18, 2026

In this report your cab and pump house were merged with the frame while the body completed paint and began initial assembly. In the next report thebody maycompleteinitialassemblyandbemergedwith thechassisatthestartofinitialapparatusassembly.

Photo 1Photo 2Photo 3Photo 4
Photo 5Photo 6

Status Update

September 03, 2026

In this report your cab was staged, the frame build continued, the pump house remained staged, and the body continued the paint process. In the next report your cab and pump house may be staged, the frame build may continue, and the body may completethe paint process.

Photo 1Photo 2Photo 3Photo 4
Photo 5Photo 6Photo 7

Status Update

August 28, 2026

In this report your cab completedinitial assembly, the frame build continued, the pump house completedinitial assembly, and the body was staged to continue through paint. In the next report your cab may be staged, the frame build may continue, the pump house may remain staged, and the body may continue the paint process.

Photo 1Photo 2Photo 3Photo 4
Photo 5Photo 6Photo 7Photo 8

Status Update

August 21, 2026

In this report your cab began initial assembly, the frame build began, the pump house was painted then staged to continueinitial assembly, and the body began the paint process with metal finishing. In the next report your cab may continue initial assembly,the frame build may continue, the pump house may continue initial assembly, and the body may continue through paint.

Photo 1Photo 2Photo 3Photo 4
Photo 5Photo 6

Status Update

August 14, 2026

In this report your cab completedthe paint process, the pump house continued initial assembly, and the body was staged. In the next report your cab may remain staged to begin initial assembly, the pump house may be painted then staged to continue initial assembly, and the body may begin the paint process.

Photo 1Photo 2Photo 3Photo 4

Status Update

August 07, 2026

In this report your cab continued the paint process, the pump house continuedinitial assembly, and the body was fabricated and staged. In the next report your cab may continue through paint, the pump house may be painted then staged to continue initial assembly, and the body may remain staged to begin the paint process.

Photo 1Photo 2Photo 3

Status Update

July 31, 2026

In this report your cab continued through paintwhile the pump house began initial assembly. In the next report your cab may continue the paint process while the pump house may continue initial assembly.

Photo 1Photo 2Photo 3

Status Update

July 24, 2026

In this report your cab remainedstaged to continue the paint process while the pump house structure was fabricated. In the next report your cab may continue through paint while the pump house may remain staged.

Photo 1Photo 2

Status Update

July 17, 2026

In this report your cab was staged to continue through paint. In the next report your cab may continue the paint process.

Photo 1

Status Update

July 10, 2026

In this report your cab completed fabrication and began the paint process with metal finishing. In the next report your cab may continue through paint.

Photo 1Photo 2

Initial Report

June 30, 2026

Congratulations -Your new Pierce apparatus is now in production! This week your cab began fabrication. In the next report your cab may continue the fabrication process.

Photo 1