Berlin NH Job# 40662

In-Production Apparatus

Job# 40662

Status Update

June 19, 2026

In this report your chassis continued assembly, the transverse continued fabrication, the torque box began initial assembly, and the body wasin queue to begin initial assembly. In the next report thetorque boxmaybemergedwiththechassis, the transverse may complete fabricationand begin the paint process, and the body may begin initial assembly.

Photo 1Photo 2Photo 3Photo 4
Photo 5Photo 6

Status Update

June 12, 2026

In this report your cab was merged with the frame, the transverse continued fabrication, the torque box arrived and was staged, and the body remained staged. In the next report chassis may be staged to continue assembly, the transverse may complete fabrication, the torque box may begin initial assembly, and the body may begin initial assembly.

Photo 1Photo 2Photo 3Photo 4
Photo 5Photo 6

Status Update

June 05, 2026

In this report your cab completedinitial assembly, the frame build began, the transverse continued fabrication, and the body remained staged. In the next report your cab may remain staged, the frame build may continue, the transverse may complete fabrication, and the body may begin initial assembly.

Photo 1Photo 2Photo 3Photo 4
Photo 5Photo 6

Status Update

May 22, 2026

In this report your cab began initial assembly, the transverse continued fabrication, and the body completed paint. In the next report your cab may continueinitial assembly, the transverse may complete fabrication, and the body may remain staged to begin initial assembly.

Photo 1Photo 2Photo 3

Status Update

May 15, 2026

In this report your cab remained staged, the transverse continued fabrication, and the body was fabricated and began the paint process in metal finishing. In the next report your cab may begin initial assembly,the transverse may complete fabrication, and the body may continue through paint.

Photo 1Photo 2Photo 3

Status Update

May 08, 2026

In this report your cab completed paint and was staged while the transverse compartment began fabrication. In the next report your cab may remain staged to begin initial assembly while the transverse may complete fabrication.

Photo 1Photo 2

Status Update

May 01, 2026

In this report your cab completedfabrication and began the paint process. In the next report your cab may continue through paint.

Photo 1Photo 2

Initial Report

April 10, 2026

Congratulations -Your new Pierce apparatus is now in production! This week your cab began fabrication. In the next report your cab may continue the fabrication process.

Photo 1Photo 2