Falmouth MA Job# 40181

In-Production Apparatus

Job# 40181

Status Update

June 12, 2026

In this report your cab began initial assembly, the frame build began, the pump house waspaintedthenstagedtocontinue initial assembly, and the body was unavailable for photos. In the next report your cab may continueinitial assembly, the frame build may continue, the pump house may continue initial assembly, and the body may be available to photograph.

Photo 1Photo 2Photo 3Photo 4
Photo 5

Status Update

June 05, 2026

In this report your cab completed paint, the pump house began initial assembly, and the body began the fabrication process. In the next report your cab may begin initial assembly, the pump house may continue initial assembly, and the body may complete fabrication.

Photo 1Photo 2Photo 3Photo 4

Status Update

May 22, 2026

In this report your cab continued through paint. In the next report your cab may continue the paint process.

Photo 1Photo 2

Status Update

May 15, 2026

In this report your cab began the paint process with metal finishing. In the next report your cab may continue through paint.

Photo 1Photo 2

Status Update

May 08, 2026

In this report your cab completedfabrication. In the next report your cab may be staged to begin the paint process.

Photo 1

Initial Report

May 01, 2026

Congratulations -Your new Pierce apparatus is now in production! This week your cab began fabrication. In the next report your cab may continue the fabrication process.

Photo 1